Annual Asphalt Resurfacing Program Update

48

We're making progress! Ten roadway segments have been resurfaced so far, with six more milled in preparation for asphalt next week. These roadways are part of the 2022 Asphalt Resurfacing Program, with many more to come. 

Here's where we are so far: 

Completed:

  • Church Street
  • Elm Street
  • North Oviatt Street
  • Old Orchard Drive
  • Pinebrooke Drive
  • Doug Avenue
  • Dana Avenue
  • Evergreen Road
  • Windsor Road
  • Barlow Road - between Stow Road and Young Road
Milled, with asphalt planned for next week:

  • Herrick Park Drive - between SR 91 and Lascala
  • Lascala Drive
  • Tamarisk Circle
  • Woodacre Drive
  • Woodspring Lane
  • Cedarwood Court (will be milled later this week)
Upcoming Milling Tentatively Week of May 23:

  • Edgar Drive
  • Topper Drive
  • Glastonbury Drive
  • Weymouth Drive
Remaining Schedule (TENTATIVE)

May 16 - 27

  • SR 91 Repairs
  • Colony Park Trails
June 6 - 17

  • Ingleside Drive
  • Silverberry Lane
  • Wilshire Park Drive
  • Leslie Drive
  • Union Drive
June 20 - 24

  • Patching
  • Sullivan Road
  • Division Street - between Main St. and College St.
  • Hudson Drive - between Terex Road and SR 91
Learn more about the 2022 Asphalt Resurfacing Program here: www.hudson.oh.us/Resurfacing

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS